12th Ave. NE (County Road 19 to Ninth St. NE) - District No. 1279

About the Project


This multi-phase project will modify the 2.5-mile rural, 2-lane stretch of 12th Ave. NE into a new urban corridor with utility improvements, curb and gutter, turn lanes, a roundabout, street lights and a shared use path. The project improvements will address future traffic demands and safety concerns. 

Project Schedule



  • Begin Date: April 2016
  • Estimated End Date: November 2018
  • Percent Complete: 99%

Road Closures


  • Road currently open to traffic
  • Spring 2018: Intermittent traffic delays during pavement marking

Upcoming Work


  • Spring 2018: 12th Ave. N. and Ninth St. N. intersection permanent markings, seeding and tree planting