Sheyenne Street Segment 1 - 13th Ave. to Beaton Dr

Sheyenne Street Segment 1 Finished Section Rendering

About this Project:

Reconstruction of a five-lane road that includes two lanes in each direction and a center turn lane to ease congestion and safety concerns. Project work includes concrete paving, curb and gutter, shared-use path, city utilities, street lights and traffic signal improvements.

Estimated Construction Cost

  • $6 million

Estimated Special Assessments

Project Schedule

  • Estimated Begin: April 2018
    • Phase 1 completion – early July
    • Phase 2 completion – early September
    • Phase 3 completion – mid September
    • Phase 4 completion – early October
  • Estimated End: June 2019
  • Project complete: 90%

Expected Road Closures

  • Head-to-head traffic shifted to northbound lanes
  • Congestion and delays likely during peak traffic

Other Impacts

  • Portion of trees removed and/or trimmed on both sides of Sheyenne Street
  • Utility locate flags are placed along 13th Avenue to help crews on site trace utilities if issues occur during the project

Completed Work

  • Underground
  • Paving
  • Curb and gutter

Current Work

  • Sidewalks
  • Driveways
  • Backfilling
  • Striping
  • Signs

Upcoming Work

  • Clean up
  • Final details