Main Avenue and 15th Street NW Traffic Signal

About this Project

North Dakota Department of Transportation project to install a traffic signal at the intersection of Main Avenue and 15th Street NW.

Estimated Construction Cost

  • $273,827

Project Schedule

  • Estimated Start Date: May 2018
  • Estimated End Date: June 2018
  • Percent Complete: 0%

Current Work

  • Underground work to begin week of May 14

Upcoming Work

  • Concrete foundation installation