September 21, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

6th Street W Realignment - District No. 1273-III
90% Complete
Estimated Begin: May 2016Estimated End: November 2017
Last Updated: September 20, 2017

Sixth Street W. is fully open. Eight Street W. is closed from Second Avenue W. to Main Avenue. Second Avenue W. is open until Eight Street W.

Completed work:

  • Eighth Street West pavement removal
  • Water main
  • Sanitary sewer
  • Storm sewer
  • Gravel
  • Eight Street W. north and southbound lanes paved
  • Sixth Street W. path in place

Upcoming work:

  • Curb and gutter
  • September paving

Last Updated: September 20, 2017

This information can be found at www.westfargond.gov