September 21, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Water Tower (Eighth Street W. & Second Avenue W.) – District No. 1260
95% Complete
Estimated Begin: May 2016Estimated End: October 2017
Last Updated: September 20, 2017

This project includes the construction of a new elevated water storage tank on the city lot adjacent to the city’s sanitation facility and deconstructing the existing water tower.

Completed work:

  • New tank complete and logos applied
  • Tower full

Upcoming work:

  • Final grading
  • Final electrical work
  • Disinfect tower
  • Change antenna over from old tower week of Sept. 18
  • Old tower demolition scheduled week of Oct. 27
  • Move master controller from old tower building to sanitation building

Last Updated: September 20, 2017

This information can be found at www.westfargond.gov