13th Avenue E. and Ninth Street E. Intersection Improvements - District No. 2243
50% Complete
Estimated Begin: August 2017Estimated End: August 2018
Last Updated: September 20, 2017

The project consists of reconstructing and widening the 13th Avenue East and Ninth Street East intersection to accommodate dual left turn lanes in all directions. The project will also involve the addition of a northbound through lane from 13th Avenue East to Seventh Avenue East, and upgrades to outdated/undersized utilities within project limits to minimize future disruptions.

Detour maps and final layout visuals were available and included in the presentation.

Completed work:

  • Phase 1: Road closures
  • Phase 1: Removals
  • Phase 1: Roadwork/base west of Ninth Street
  • Phase 1: Sanitary sewer force main
  • Phase 1: Water main
  • Phase 1: Storm sewer
  • Phase 1: Road base

Upcoming work:

  • Phase 1: Paving preparations
  • Phase 1: Pave eastbound week of Sept. 18
  • Phase 1: Pave westbound week of Sept. 25
  • Phase 1: Mainline paving
  • Phase 1: Turn lanes
  • Phase 1: Curb and gutter
  • Phase 1: Sidewalks
  • Phase 1: Street lights
  • Phase 1: Signing
  • Phase 1: Striping

Last Updated: September 20, 2017