Water Tower Rehabilitation - 12th Avenue E. & Meadow Ridge - District No. 1302
65% Complete
Estimated Begin: May 2017Estimated End: October 2017
Last Updated: September 20, 2017

We will rehabilitate and apply new protective coatings to the Meadow Ridge and 12th Avenue E. water towers. Crews are currently working on the internal sewer work. The Meadow Ridge Tower rehabilitation activity is expected to begin late May or early June and finish up in August. The 12th Avenue E. rehabilitation is expected to start in August. The tanks will be disconnected from the water system while work is performed.

No noticeable changes to water service are expected.

Progress:

  • Meadow Ridge Tower: 100%
  • 12th Avenue Tower: 30%

Completed work:

  • Meadow Ridge tower

Upcoming work:

  • 12th Avenue tower to begin in September