September 21, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Emergency Vehicle Preemption - District No. 2242
99% Complete
Estimated Begin: May 2017Estimated End: September 2017
Last Updated: September 20, 2017

Project to install GPS-based emergency vehicle preemption at stop lights.

Completed work:

  • All equipment installed

Upcoming work:

  • Testing intersections

Last Updated: September 20, 2017