Eighth Avenue NW and 26th Street NW Paving, Utilities and Pond - District No. 2240
65% Complete
Estimated Begin: October 2016Estimated End: November 2016
Last Updated: September 20, 2017

This multi-phase project involves utilities, a storm water retention pond, and paving. The project will include paving of Eighth Avenue NW from Ninth Street West to 26th Street NW, as well as the reconstruction and paving of 26th Street NW from Eighth Avenue West to First Avenue NW. 

Road Closures:

  • Eighth Avenue embankment work - expect delays

Progress:

  • Paving: 40%
  • Utilities and pond: 90%

Completed work:

  • Eighth Avenue concrete returns
  • All underground utilities
  • West Fargo Fifth Addition

Upcoming work:

  • 26th Street NW punchlist
  • Eighth Avenue NW embankment in October
  • Lift force main and outfall
  • Signing
  • Light poles
  • Striping
  • 26th Street final work
  • Fabric followed by gravel Fall 2017
  • Pave Eighth Avenue NW spring 2018