September 21, 2017
West Fargo Streets

Several road projects are underway in the City of West Fargo.  Check regularly for project updates.

Elmwood Court Traffic-Calming Improvements - District No. 2246
25% Complete
Estimated Begin: August 2017Estimated End: October 2017
Last Updated: September 20, 2017

A traffic-calming project to install a roundabout and speed table in the Elmwood Court development begins Tuesday, Aug. 29. The project is estimated for completion Oct. 15, 2017, and will be split into two phases.

The intersection of 19th Avenue W. and Seventh Street W. is closed as crews begin installing a roundabout during the first phase. Residents in the area will have access to their homes, while through traffic will be detoured around the intersection. Motorists are encouraged to drive slowly and follow posted traffic signs to maintain safety.

Following the completion of the roundabout, phase two will begin with crews constructing a speed table on 19th Avenue W. between Sixth Street W. and Sheyenne Street. This construction will close through traffic at 19th Avenue W. and drivers will need to use 13th Avenue W. to enter the development.

Detour Map

Completed work:

  • Curb and gutter
  • 30% roundabout paving

Upcoming work:

  • Pave medians
  • Start speed table early October

Last Updated: September 20, 2017