North Sheyenne Street Project

◄ Back
October 1, 2021

Construction Update - Oct. 1, 2021

Road closures:
• Sheyenne Street is closed from 2nd Avenue W. to Main Avenue W.
• Traffic is detouring to 1st Street and Morrison Street for local access.
• Traffic is detouring to Ninth Street E. for thru traffic between Main and 13th Avenues W.

Progress:
• In phase 3, crews prepped the road for paving and were able to pave the southbound lane today.
• Next week, crews in phase 3 will move to paving the northbound lane and parking.

Schedule:
• The project is currently on schedule for phase 3.

Upcoming information meetings:
• Online public update 11:30 a.m. Tuesday, Oct. 5

A view of paving preparation in phase 3 looking no