North Sheyenne Street Project

◄ Back
July 16, 2021

Construction Update - July 16, 2021

Road closures:
• In phase 1, Sheyenne Street is open from Seventh Avenue W. to Fourth Avenue W.
• In phase 2, Sheyenne Street is closed from Fourth Avenue E. to Second Avenue W.
• Traffic is detouring to Sukut Street and Morrison Street for local access and Ninth Street E. for thru traffic between Main Avenue and 13th Avenue.

Progress:
• In phase 1, the road is fully open for thru traffic. Temporary lane closures may occur in the next few months for landscaping.
• In phase 2, crews completed paving Sheyenne Street’s northbound lanes.
• Business alley access for properties on Sheyenne Street’s east side between Second and Third Avenues W. moved to Second Avenue E.

Schedule:
• The project is nearly complete in phase 1.
• The project is currently on schedule for phase 2.

Upcoming information meetings:
• Online public update 11:30 a.m. Tuesday, July 27.

Updated phase 1 and phase 2 traffic mapView of phase 1 looking south Next Photo
Facebook Twitter Email