North Sheyenne Street Project

◄ Back
July 9, 2021

Construction Update - July 9, 2021

Road closures:
• In phase 1, Sheyenne Street is open from Seventh Avenue W. to Fourth Avenue W. with temporary lane closures.
• In phase 2, Sheyenne Street is closed from Fourth Avenue W. to Second Avenue W.
• Traffic is detouring to Sukut Street and Morrison Street for local access and Ninth Street E. for thru traffic between Main Avenue and 13th Avenue.

Progress:
• In phase 1, final cleanup began this week and the road is expected to fully open next week.
• In phase 2, crews completed hand pours of Second and Third Avenue W. off of Sheyenne Street. Crews also plan to pave the northbound lanes of Sheyenne Street early next week, with street tie-ins to follow.

Schedule:
• The project is currently on schedule for phase 1.
• The project is currently on schedule for phase 2.

Upcoming information meetings:
• Online public update 11:30 a.m. Tuesday, July 27.

View of phases 1 and 2 looking north