June 11, 2021

Construction Update - June 11, 2021

Road closures:
• Sheyenne Street is closed from north of Seventh Avenue W. to Fifth Avenue W. and from Fourth Avenue W. to Second Avenue W.
• Traffic is detouring to Sukut Street and Morrison Street for local access and Ninth Street E. for thru traffic between Main Avenue and 13th Avenue.

Progress:
• In phase 2, crews completed most of the removals and began underground utility work.
• In phase 1, driveways, sidewalks, and streetscaping planter boxes were poured.

Schedule:
• Phase 1 is expected to be completed by the end of June.
• The project is currently on schedule for phase 1.
• The project is currently ahead of schedule for phase 2.

Upcoming information meetings:
• Online public update 11:30 a.m. Tuesday, June 15.
• Project update meeting 5:15 p.m. Wednesday, June 23.